Potable Water :
First Stage works for potable water supply 75 village involved in 240 villages projects (2 Villages - Esmaelia) :
Project Description:
- Water Networks:
- U.P.V.C. pipelines of 100 : 200 mm dia. & 162 km long and 10 bar working
pressure .
- H.D.P.E. pipelines of 300 : 500 mm dia. & 25.46 km length and 10 bar working
pressure .
- Elevated tank 1000 m3 capacity & 50 m height.
- Crossings:
- Over Piles for canals & drains :
- 45 nos steel crossings 100 : 500 mm dia. And total length 915 m.
- 3 nos by controlled drilled 300 : 500 mm dia., total length 510 m.
- Additional works for 5 pipelines networks villages not supplied by water.
Project value & Date:
- The Value of contract is 50 million EGP
- The Contract Date 03/08/2005
- The End Date 2/7/2007