Potable Water :

Potable water and wastewater networks at Nahia village-Giza Governorate

Project value & Date:

  • The Value of contract is 160.349026 Million EGP
  • The Contract Date 4/6/2008
  • The End Date 12/31/2023

Project Description:

* Potable water networks 63.3 km length :
1- UPVC pipelines form 110 : 315 mm dia., 62650 m length.
2- GRP pipelines from 400 : 600 mm dia.,3150 m length.
3- DI pipeline 800 mm dia.,35 m length.
4- Valves, Valve chambers,house connections and fire hydrant.
* Crossing:
1-Steel  and Ductile cast Iron crossings pass over the canals and drainages. 
* Tanks:
1-Reservoir 2500 m3 capacity, Transformer and generator buildings.
* Rehabilitation of existing pipelines(removal old pipelines and re-installtion new pipelines).
* Gravity networks 62.8 km length:
1-V.C. pipelines 7ً : 26  ًdia.,59.819 m length , manholes and house connections . 
-RC  of dia 600-800and length 2.293 km
* pump station 14 m dia., 14.5 m hight & annex building + 4 tunnel crossing under canals and drainages .
* Pressurised pipeline:
1- DI pipeline 600 mm dia. And 0.653 km long 