Société Egyptienne D’entreprises

Housing & Tourist Villages and their Utilities :

Water & Wastewater networks for Abu El-Houl Area - new cairo city.

Project value & Date:

  • The Value of contract is 31.84618 Million EGP
  • The Contract Date 4/29/2007
  • The End Date 4/30/2011

Project Description:

* Potable water networks:
 - UPVC pipelines from 110 : 400 mm dia. , 107.16 km length.
* Wastewater networks:
 - UPVC pipelines from 160 : 500 mm dia. , 28.467 km length.
 - VC pipelines flexible joint from 24'':28" dia., 31.83 km length.
 - 612 sumps to drain the rains water . 