Housing & Tourist Villages and their Utilities :

Infrastructure (Potable water-wastewater-irrigation, electricity - communication and civil works) for the areas first precedence for the new administrative capital+ a compact unit to get ride of El Masa hotel wastewater disposal

Project value & Date:

  • The Value of contract is 108.404144 Million EGP
  • The Contract Date 4/6/2016
  • The End Date 12/31/2023

Project Description:

** Wastewater Networks:
* UPVC  and polyethylene pipelines 200 mm dia.: 1200 mm  with  length 13.8 km
** Potable Water Network and  irrigation network::
* UPVC pipelines 160:700 mm dia.,  with  length 16 km
* temporary water line + tunnel crossing with length 4 km
** Road Works 3.5 km length 